Installation guides
Internal vertical wall panels — factory type environment
- Check floor is level and mark line for fit of angle.
- Drill and fix floor fixings at 300mm centres. See drawing number FMV-05C.
- Repeat this action for one of the head angles only.
- Apply continuous bead of sealant to inside edge of both angles (head and base).
- Offer the vertical panel up to the angle and ensure panel is plumb before fixing.
- Face fix both the head and the base angles to the panel at 300mm centres.
- Hold panel in position and offer the next panel to it.
- Slide panel into the next panel, ensure panel cores fit tightly together – if necessary use a 3mm spacer to ensure consistent joint widths.
- Pack any voids with mineral fibre – minimum density 23 kg/m3.
- Fix second panel to angles repeating above.
- Lay continuous bead of sealant to both floor and panel face in readiness for positioning
of second (face) angles.
- Repeat this in preparation for fixing of the head angles also.
- Fix angles to panels at 300mm centres.
- Apply continuous bead of mastic to panel/panel joints ensuring that no gaps are present.
- See installation drawings for additional information.